From the air, wood walls now stand around the footprint of the new Church, and steel frames rise through the middle.

The framing crew is installing the structural shear walls. Plywood is going on over the studs, with hold-down anchors and metal straps that tie those walls to the foundation.

The truss crew is setting the second-floor trusses.

In the sanctuary, two moment frames are standing. The beams are bolted into the columns. A lift is holding a beam while a worker makes the connection.

Why this phase matters

Shear walls and moment frames keep the building from racking sideways in the wind or in an earthquake.

A shear wall is a wood wall made stiff by plywood. It braces the rooms beside it. A moment frame does that work in steel, so the sanctuary can stay open.

The second-floor trusses carry the floor above these walls.

We’re grateful for the crew’s careful work and for everyone praying over this project.